Timeline and documents
Below are some key milestones in our anticipated delivery timetable for the project over the next few years. Some of these timescales are subject to receiving all the necessary approvals that we need before we can start construction and the Department for Transport approving the Full Business Case, which confirms their full funding contribution.
2026
- Surveys and preparatory work on site, including work by National Gas Transmission to divert two gas mains (necessary before construction on the new road can start)
- Design and build contractor appointed
- Costain awarded the contract to complete the detailed design and build the road
2027
- Full Business Case approval, releasing Department for Transport funding needed for construction
- Further preparatory and ecological mitigation work on site
- Start of construction
2028
West Winch Housing Access Road open for use
2029
Work related to the project completed on site
Key documents
2 March 2026 - Cabinet Report
Cabinet Report - 2 March 2026 - Item 15, page 732
1 December 2025 - Cabinet Report
Cabinet Report - 1 December 2025 - Item 9, page 83
Planning application documents - 26 November 2025
Planning application documents
2 September 2024 - Cabinet Report
Cabinet Report - 2 September 2024 - Item 11, page 164
Outline Business Case - September 2024
Outline Business Case (PDF, 4 MB)
4 December 2023 - Cabinet report
Cabinet Report - 4 December 2023 - item 10, page 243
4 September 2023 - Cabinet report
Cabinet Report - 4 September 2023 - item 10, page 64
8 March 2021 - Cabinet Report
Cabinet Report - 8 March 2021 - item 11, page 108
2 September 2019 - Cabinet Report
Cabinet Report - 2 September 2019 - item 9, page 65