Timeline

We are working to the following timetable, some of which is subject to all the necessary statutory processes for a project of this kind being completed.

  • Winter 2018/19 – Options consultation
  • Spring 2019 – Preferred route announcement
  • Autumn 2021 – Planning process complete
  • Late 2022 – Start of construction
9 November 2018

EDT Committee Report

12 October 2018

EDT Committee Report

20 October 2017

EDT Committee Report and WSP Technical Scoping Report

15 September 2017

EDT Committee Report

8 September 2017

Business and Property Committee Report

8 July 2016

EDT Committee report

June 2016

Mouchel Technical Report Published (commissioned May 2016)

 29 January 2016

 EDT Committee report

18 September 2014

EDT Committee Report on Preliminary Option Report - Mott MacDonald

Report to Cabinet advising of the further work being carried out on the alternative route options for a Norwich Northern Distributor Road (NDR) and putting forward proposals for moving the scheme forward.  Develop mitigation measures for all eastern and western route options and the impacts on the Wensum Special Area of Conservation (SAC).

Was this webpage helpful?