Cookie Consent by PrivacyPolicies.com Timeline and documents - Norfolk County Council

Timeline and documents

Following the announcement of the preferred route for the Norwich Western Link in July 2019, the project team have been carrying out work to refine and inform the detailed design of the road and associated measures.

We have also started work on an Outline Business Case for the project, which is the next document we are required to submit to the Department for Transport. This will go into more detail than the Strategic Outline Business Case which was submitted in 2019 and approved in May 2020.

We are working to the following timetable, some of which is subject to all the necessary statutory processes for a project of this kind being complete:

  • 2020 – Outline Business Case completed and submitted
  • Early 2021 – Contractor appointed
  • Mid-2021 – Pre-planning application public consultation
  • 2023 – Start of work on site
  • Late 2025 – Road completed and open to traffic

Key documents 

1 May 2020

2019 Ecology Survey Reports

3 February 2020

Cabinet Report

15 July 2019

Cabinet Report

8 March 2019

EDT Committee Report

9 November 2018

EDT Committee Report

12 October 2018

EDT Committee Report

20 October 2017

EDT Committee Report and WSP Technical Scoping Report

15 September 2017

EDT Committee Report

8 September 2017

Business and Property Committee Report

8 July 2016

EDT Committee report

June 2016

Mouchel Technical Report Published (commissioned May 2016)

 29 January 2016

 EDT Committee report

18 September 2014

EDT Committee Report on Preliminary Option Report - Mott MacDonald

Report to Cabinet advising of the further work being carried out on the alternative route options for a Norwich Northern Distributor Road (NDR) and putting forward proposals for moving the scheme forward.  Develop mitigation measures for all eastern and western route options and the impacts on the Wensum Special Area of Conservation (SAC).

Was this webpage helpful?